All Project Status Updates

  • Updated: 6 months 2 weeks ago
    This project includes adding Greensand Filters to the existing treatment system to remove iron and manganese in the raw water....

    Status Update:

    UPDATE: The building and filter construction will start in December 2017.
  • Updated: 6 months 2 weeks ago
    Carrollton Utilities and Carroll Co. Water District #1 have teamed up to replace 100 year old water lines in downtown...

    Status Update:

    The project will be submitted for SRF funding consideration in December 2017 with award of funds in May 2018.